Stage 2 works have now been completed with titles expected later this month!

Construction of Stage 3 is progressing well with sewer, drainage, kerb, electrical and NBN works completed and is expected to be fully completed by the end of September. Drainage and sewer works have commenced on Stage 4 whilst early site works are now also underway on Stage 5. Landscape works are scheduled to commence later this month, including the multi-million dollar St. Georges Boulevard entry treatment and the Stage 1 neighbourhood park!